Conclusion on compliance with technical regulations. What is AIA for a new building: what is it, how to get it and why

29.12.2016

For introduction construction site into operation after construction, repair and other work, appropriate documents are required, one of which is the AIA.

Decoding and general concept

Not everyone is familiar with the concept of AIA, and they usually start looking for information about the term and its decoding only in a personal collision. What does this abbreviation mean?

So, AIA in construction is a conclusion on compliance. Means the compliance of the erected or capitally reconstructed object with all the rules and norms of technical regulations, SNiPs and project documentation... This document is issued only after a series of appropriate checks and the full suitability of the construction site and its individual parts for settlement and other anticipated needs.

Before the final inspection, which the building undergoes to obtain an opinion on conformity, many control procedures are carried out at all stages of construction and for each individual part. By the time a permit for operation is received, dozens of documents on current supervisory operations and inspections have been accumulated.

Before the final check is carried out:

  • trial runs of heating, electrical systems, drainage and ventilation mechanisms of the building;
  • individual testing of parts, equipment and technical components;
  • for major repairs under the contract - the acceptance certificate.

Who to contact

Who issues the AIA? Construction is an industry that is completely regulated by the state. Without the permission of government agencies, the process of building a house, factory or pool is impossible and punishable. Therefore, the issuance of all documents for permission to occupy buildings and their use is carried out by state bodies.

In the case of the conclusion of compliance, the issuing party will be the state building supervision authority. He monitors all the activities of the developer from the first stages of construction and conducts constant periodic checks, pointing out shortcomings and inconsistencies with certain requirements.

The supervisory authority has a period of up to one month for the final check, and 10 days for the issuance of an opinion from the date of application.

Nuances

If the necessary checks did not take place on time and at the construction stage, especially in new buildings, which are under strict supervision, it will be problematic to obtain an AIA.

The developer will have to fuss to settle this issue, otherwise the new building or the building after the renovation will never go into operation.

Reasons why the developer is refused to receive an opinion on compliance:

  1. The supervisory authority was not informed on time about the start of development;
  2. The regularity of supervision has been disrupted;
  3. The defects that were pointed out to the developer at a certain stage of construction have not been eliminated;
  4. Lack of supervision due to the fault of the developer.

In such situations, in order to obtain an AIA, they turn to an independent specialized organization for services. She must have a license and thoroughly conduct a survey of the building. Only upon approval of the compliance of the building with all standards, you can re-apply for an opinion on compliance.

This is a required document.

What documents are attached to the application for issuing a permit to commission an object is spelled out in part 3 of article 55 Urban Development Code Russian Federation.

Extract from the Order of the Federal Service for Environmental, Technological and Nuclear Supervision of December 26, 2006 N 1129 "On Approval and Implementation of the Procedure for Conducting Inspections in the Exercise of State Construction Supervision and Issuance of Conclusions on the Compliance of Built, Reconstructed, Repaired Capital Construction Facilities with the Requirements of Technical Regulations (rules and regulations), other regulatory legal acts, project documentation

APPROVED BY
by order of the Federal Service
on environmental, technological
and atomic supervision
dated December 26, 2006 N 1129


ORDER
conducting inspections in the implementation of state construction
supervision and issuance of conclusions on the conformity of constructed, reconstructed,
renovated capital construction requirements
technical regulations (norms and rules), other regulatory
legal acts and project documentation
RD-11-04-2006


...

IV. Features of the final check in the implementation
state construction supervision


25. The final inspection is appointed by an official of the state construction supervision body within 7 working days after receiving a notice from the developer or customer about the completion of construction, reconstruction, overhaul of capital construction projects, drawn up according to the model given in Appendix No. 10 to this Procedure. This notice is sent by the developer or customer after the actual completion of construction, reconstruction, overhaul of the capital construction facility, elimination of all violations committed during construction, reconstruction, overhaul of the capital construction facility, execution of executive documentation related to the performance of all construction, reconstruction, capital repair of a capital construction object, as well as the use of building materials (products).

The developer or customer is notified of the final inspection by an official of the state construction supervision body in accordance with paragraph 9 of this Procedure.

26. During the final inspection, the inspection procedure provided for in Chapter III of this Procedure must be observed, and the following shall be taken into account:

A) the completed, reconstructed, repaired capital construction facility is subject to visual inspection in full (including individual work performed, building construction, sections of engineering and technical support networks and applied Construction Materials(products);

B) all acts (instructions, notifications) on the elimination of violations (shortcomings) identified during the implementation of state construction supervision and construction control are subject to verification.

27. The result of the final check is drawn up in an act drawn up according to the model given in Appendix No. 7 to this Procedure. This act is the basis for the application of the developer or customer for the issuance of an opinion on the compliance of the constructed, reconstructed, repaired capital construction facility with the requirements of technical regulations (norms and rules), other regulatory legal acts and project documentation.

28. The body of state construction supervision, within 10 days after receiving the application from the developer or customer specified in paragraph 29 of this Procedure, issues an opinion on the compliance of the constructed, reconstructed, repaired capital construction facility with the requirements of technical regulations (norms and rules), other regulatory legal acts and design documentation, and in the absence of grounds for issuing an opinion, makes a decision to refuse to issue such an opinion in compliance with the requirements of paragraphs 17-20 of the Regulations on the implementation of state construction supervision in the Russian Federation, chapter V of this Procedure.

V. The procedure for issuing conclusions on the conformity of the constructed,
reconstructed, refurbished capital facilities
construction to the requirements of technical regulations
(rules and regulations), other regulatory legal acts
and project documentation


29. The conclusion of conformity, drawn up according to the model given in Appendix No. 11 to this Procedure, or a decision to refuse to issue such an opinion, drawn up according to the model given in Appendix No. 12 to this Procedure, is issued by an official of the state construction supervision body to the developer or to the customer within 10 working days from the date of the relevant application for the issuance of an opinion.

30. The conclusion of conformity or the decision to refuse to issue such a conclusion is drawn up in 2 copies, each of which is signed by an official of the state construction supervision body who carried out the final check, and approved by the order (order) of the head (the person performing his duties, or a person, which has the right to issue such an order (order) in accordance with its powers and distribution of responsibilities) of the state construction supervision body.

31. The first copy of the conclusion of compliance or the decision to refuse to issue such an opinion is sent (handed) by an official of the state construction supervision body to the developer or customer who applied for the issuance of the opinion, or their representatives on the basis of a duly executed document on representation. The second copy of the opinion on compliance or the decision to refuse to issue such an opinion remains in the file of the state construction supervision body.

The opinion is handed over to the authorized representative of the customer or developer on the basis of the relevant document on representation. In case of refusal to receive (sign) the conclusion by the representative of the developer or customer, the document is sent by registered mail with notification.

32. The adoption by the state construction supervision body of a decision to refuse to issue an opinion on conformity does not prevent the developer or customer from re-applying for a compliance conclusion after the reasons that served as the basis for the adoption of the said decision by the state construction supervision body are eliminated.

To put a construction site into operation after construction, repair and other work, the relevant documents are required, one of which is the AIA.

Decoding and general concept

Not everyone is familiar with the concept of AIA, and they usually start looking for information about the term and its decoding only in a personal collision. What does this abbreviation mean?

So, AIA in construction is a conclusion on compliance. Means the compliance of the erected or overhauled facility with all the rules and norms of technical regulations, SNiPs and project documentation. This document is issued only after a series of appropriate checks and the full suitability of the construction site and its individual parts for settlement and other anticipated needs.

Before the final inspection, which the building undergoes to obtain an opinion on conformity, many control procedures are carried out at all stages of construction and for each individual part. By the time a permit for operation is received, dozens of documents on current supervisory operations and inspections have been accumulated.

Before the final check is carried out:

  • trial runs of heating, electrical systems, drainage and ventilation mechanisms of the building;
  • individual testing of parts, equipment and technical components;
  • for major repairs under the contract - the acceptance certificate.

Who to contact

Who issues the AIA? Construction is an industry that is completely regulated by the state. Without the permission of government agencies, the process of building a house, factory or pool is impossible and punishable. Therefore, the issuance of all documents for permission to occupy buildings and their use is carried out by state bodies.

In the case of the conclusion of compliance, the issuing party will be the state building supervision authority. He monitors all the activities of the developer from the first stages of construction and conducts constant periodic checks, pointing out shortcomings and inconsistencies with certain requirements.

The supervisory authority has a period of up to one month for the final check, and 10 days for the issuance of an opinion from the date of application.

Nuances

If the necessary checks did not take place on time and at the construction stage, especially in new buildings, which are under strict supervision, it will be problematic to obtain an AIA.

The developer will have to fuss to settle this issue, otherwise the new building or the building after the renovation will never go into operation.

Reasons why the developer is refused to receive an opinion on compliance:

  1. The supervisory authority was not informed on time about the start of development;
  2. The regularity of supervision has been disrupted;
  3. The defects that were pointed out to the developer at a certain stage of construction have not been eliminated;
  4. Lack of supervision due to the fault of the developer.

In such situations, in order to obtain an AIA, they turn to an independent specialized organization for services. She is required to have a license and carefully conduct a survey of the building. Only upon approval of the compliance of the building with all standards, you can re-apply for an opinion on compliance.

Share with friends or save for yourself:

Loading...