A simple sample estimate for the construction of a house will help the owner deal with the final project cost.

The fact that any business must begin with calculations is known to every person. Get ready to paste wallpaper in the house - calculate what costs will be needed for wallpaper, glue, putty, painter's work. If you want to build a table with your own hands - calculate the cost of boards, screws, PVA glue.

When building a house, it is necessary to take into account all the construction stages and the costs of them. Such indicators are concentrated in the working draft in the section of the estimate documentation.

How to make an estimate for the construction of a house without loss and revision?

About how to make an estimate for the construction of a house, it is known to estimators, foremen, other categories of engineers and builders. Ordinary people who are not associated with construction work, but who have started the construction of a dwelling, have some idea of ​​\u200b\u200bthis. Their desire is clear: they do not want to overpay extra amounts. If a person is persistent and purposeful, it will not be difficult for him to carry out the calculations himself. Sample estimates for the construction of a house are widely presented on the Internet.

Estimated documentation is prepared on the basis of calculations, which presents items with indicators:

  • serial number;
  • numbers of estimates and calculations;
  • names of the construction stage;
  • the estimated cost, which consists of the cost of construction and installation works, the use of materials, and other expenses;
  • total estimated cost.

Estimated calculations signed by the compiler's management and the customer are considered a monetary document, which is the basis for the actual performance of work, participation in the tender, etc.

When drawing up an estimate for the construction of a house, all important and secondary positions are taken into account. Sometimes it seems to the customer that the inclusion of a particular expense item is not necessary at all. But in the course of construction, unforeseen expenses unaccounted for in the documentation “loom”. The customer understands this and lays in the documentation 5-10% for unforeseen overhead costs. This may be funds aimed at obtaining permits from fire authorities, gas workers, electricians, water suppliers and other permitting authorities, or other types of expenses.






A sample estimate for the construction of a house made of wood covered with metal tiles

We will try and introduce you to a sample estimate for the construction of a house made of wood with an area of ​​150 sq.m

Object name: wooden house
Technology: log construction
Total area: 150 sq.m
Total Estimated Cost: 1 million 630 thousand 244 rubles (1 630 244 rubles)
Base: design documentation, drawings

  • 1. Carrying out geological, hydrogeological, topographic survey work on the site for the construction of a house (sq.m) 200x100 = 20,000 rubles
  • 2. Ground work to remove the humus layer of soil (cubic meters) 10x450 = 4500 rubles
  • 3. Digging a trench under the foundation with a width of 600 mm (cubic meters)
    50х575=28 750 rub
  • 4. Manual trench leveling with soil compaction (m2)
    22х689=14 960 rub
  • 5. Backfilling of sand and gravel into the ditch (m3) 12x1200=14400.
    This also includes the cost of the material 12x600 = 7200
    Total for this position 14 400 +7200= 21600
  • 6. Installation, and after complete hardening, dismantling of the formwork (m2)
    60x100=6000;
    this also includes the cost of renting formwork 60x250=15000;
    total for this position 6000+15000= 21000



  • 7. Binding of longitudinal steel reinforcement D12 and transverse reinforcement D8 (m3). The consumption of 60 kg of rolled metal per 1 m3 of concrete is envisaged.
    Work 20x1800=36000;
    the need for fittings D12 and D8 20x60 = 1200 kg. If the price of reinforcement for 1 ton is 26,000 rubles, then the cost of the material is 1.2x2600 = 31200.
    Total for the 7th position 36000+31200= 67200
  • 8. Pouring concrete mixture 20x2500=50000;
    cost of concrete 20х5000=100 000
    The total cost of the 8th pos. 50000+100000=150000
  • 9. Waterproofing of vertical foundation walls (using hot bitumen applied twice) (m2) 80x150=12000
    Cost of materials 80х45=3600
    Total for the 9th position 12000+3600=15600
  • 10. Grinding logs with a plane (linear m) 572х66=37752
  • 11. Fine, 2-sided grinding of logs (m2) 572х400=228800
  • 12. Alignment of corners (pcs.) 8х1500=12000
  • 13. Rolled logs (pcs.) 2х1500=3000
  • 14. Carrying out works on decontamination of logs with special solutions (lin.m) 580x15=8700
    cost of septic tanks 580х20=11600
    Total 8700+11600=20300
  • 15. Installation of a log house on the foundation (m2) 150x550=82500;
    materials 150x1500=225000;
    total for the 15th pos. 82500+225000=307500
  • 16. Double-sided curling of tow, (linear m) 572x50 = 28600;
    material 572x3=1716;
    total for the 16th pos. 28600+1716=30316
  • 17. Double-sided caulking of a log house, (linear m) 572x140=80080;
    material 572x3=1716;
    total for the 17th pos. 80080+1716=81796
  • 18. Cutting window and door openings, installation of windows and doors (pcs.)
  • 14x2000=28000;
    material 14x2500=35000;
    total for the 18th pos. 28000+ 35000=63000
  • 19. Installation of beams, installation of ceilings, subflooring (m2)
    128x80=10240;
    materials 5522.38x6.7=37000;
    total for the 19th pos. 10240+ 37000=47240
  • 20. Clapboard lining of walls, ceiling, roof, finishing flooring (m2) 390х325=126750
    materials 7586.2x5.8=44000
    only on the 20th pos. 126750+44000=170750
  • 21. Coloring (m2) 144х50=7200;
    paint and other materials 144x70=10080;
    total 7200+10080=17280
  • 22. Assembly of the roof with the installation of the lathing (m2) 135x750=101250;
    materials 5400x2.5 = 13500;
    total 101250+13500=114750
  • 23. Installation of metal tiles (m2) 135x300=40500;
    the cost of metal tiles and fasteners 135x350=47250;
    total 40500+47250=87750
  • 24. Finishing the plinth with stone (m2) 22x2200 = 48400;
  • 25. Installation of entrance metal doors, 2 sets (m2) 2х3500=7000;
    material 2x4500=9000;
    total for the 25th pos. 7000+9000=16000

Total estimated: 1 630 244 rubles
including:

  • - for materials: 592,862 rubles
  • - for the performance of work: 1 037382 rubles

As you can see, it is not very difficult to make an approximate estimate for building a house if you know the consumption of materials, standard prices and current prices. The article also provides a sample estimate for a residential building made of gas blocks (see fig.).

Conclusion

Each person can calculate the cost of construction. But experts do it more skillfully and competently. Sometimes they overestimate the amounts for individual items. In order to adjust the indicators, the owners themselves can perform the calculations or turn to the help of other organizations.